In connection with the end of the holiday season, "Chernomorie" will resume the repair of several sections of the A-147 highway in the section from the points of the Lazarevsky district towards the city center. In this regard, reverse traffic will be gradually introduced at the repair sites. From September 15, repairs will begin on sections km 117+400 - 117+800 and km 138+500 - 139+900 in the areas of Volkonka and Verkhneakornaya Shchel settlements. On the first of them, work will last until the beginning of December, on the second - until the end of October.
From September 20, repairs will begin on the section km 159 + 500 - 161 (Batumi highway). Here the road builders plan to finish the work before the end of November.
On October 1, repair work will begin on three more sections between the settlement of Yakornaya Shchel and the settlement of Uchdere. They will last until the end of April 2023 with a break for the New Year holidays. Reverse traffic will be regulated by traffic lights.